Abstract
AbstractThe impact of project delays is usually intolerable
and difficult to recover from. A significant number of
projects dont finish on time or arent completed up to the
specified quality and are subject to cost and time overruns.
Public projects in the Kingdom of Saudi Arabia (KSA)
claimed losses of the order of $ 40 Billion per annum as a
result of project overruns and many were delivered below
quality standards. A proposed solution involving eight
stages was developed in order to tackle most of the project
delay issues that were determined by the author and
accordingly ranked based on severity and frequency. These
stages have detailed processes with control gates so that
these projects will be moved steadily meeting all
requirements at each entry gate. The eight stages are; the
proposal stage, preliminary review investigation stage,
validation stage, classification stage, consultation-a stage,
consultation-b stage, kickoff stage, and finally
handover takeover stage. All selected projects will be
gathered at the proposal stage and then will be
preliminarily reviewed before they move to the stage of
validation. In the validation stage, the unnecessary projects
will be postponed or canceled by the higher authority of
projects which is proposed to be created. The classification
stage is a very critical stage where all filtered projects will
be classified based on eleven criteria. A scoring method was
developed with respect to these criteria. Accordingly each
project gets a proper parachuting so that the consultation-A
phase would confirm the projects adequacy, readiness, and
the availability of all related documents and studies. The
Consultation-B stages role is to link the top countrys vision
2030, objectives, and targets. Accordingly, the higher
consultants committee will assure the compliance of the
government strategy of in-house sourcing plan, technology
transfers and national recruiting Saudization. The last
two stages are the kick-off and the takeover which will be
referred to the contract management, final project review,
and proper closing process. The project classification
matrix was used as an effective tool for many projects
classification in KSA. The paper classified King Abdullah
Stadium in KSA-2014 Category-A with a score of 44 out 55
which accordingly is subject to the highest project
management level of control. The ultimate goal of this new
project management protocol is to establish a higher
projects authority to assure the implementation of 2030
strategy with special guidance and support with respect to
the main project delay factors on the major infrastructural
projects.1
Original language | English (Ireland) |
---|---|
Journal | Journal of Advanced Management Science |
Volume | 6 |
Issue number | 3 |
DOIs | |
Publication status | Published - 1 Sep 2018 |
Authors (Note for portal: view the doc link for the full list of authors)
- Authors
- AbuKwaik,A; Fallon,EF; Donnellan,P;